| HOME| SITEMAP | FORUM HTML | DIRECTORY | SITEMAP | FORUM-RSS | |

 

Main Menu

  Home

  Classifieds

  Downloads

  Forum

  E-Greetings

  Chat Room

  Flash Games

  Game Challenge

  Wallpapers

  Web Directory

  Vehicles Prices

 

E-BOOKS

  Business E-Books

  Computer Books

  Cooking E-Books

  Health E-Books

  How Stuff Works

 

REAL KARACHI

  About us

  Contact us

  Link Exchange

  Advertise With us

   
 

 

Powered by WordPress

   

KARACHI BLOGS ( MOBILE BLOGS, NOKIA, SAMSUNG, SONYERICSSON BLOGS)

   

KARACHI INFORMATION & MOBILE BLOGS

 

April 25, 2008

Construction of KPP suffers delay

Filed under: Karachi News — Faraz Ahmed @ 12:09 am

Construction works of Korangi Power Plant (KPP) continues to remain halted during the last 8 months in view of non payment of dues to Seimens by Karachi Electric Supply Corporation (KESC).
According to Geo News officials of KESC said that electricity production suffered delay because of discontinuation of Grid Station’s construction work.     The original schedule Korangi Power plant was to generate 85 MW electricity from April 2008 while the supply of as much power from the same plant from July 1 2008.
Siemens Pakistan was entrusted with the construction of Grid Station but due to non-payment of dues by KESC it has now approached the court.

 
 